List of projects implemented in romania by OMS-Hungaria kft./ OMS-România s.r.l.

Print

Negreşti Oaş, Satu Mare county

-    Mechanical-biological wastewater treatment plants with a capacity of
Q = 2.500 m3/day;
-    PHARE program;
-    Construction of 11.000 m sewage system;
-    Implementation period: 2003 (11 months);
-    Beneficiary: Negrești Oaș Local Council;
Value: 1 900 000 Euro.

Corund, Harghita county

-    Modular mechanical-biological wastewater treatment plants consisting of 3   modules, with a capacity of Q = 900 m3/day;
-    Construction of 14.000 m sewage system;
-    4 pumping stations;
-    SAPARD program;
-    Implementation period: 2005-2006 (12 months);
-    Beneficiary: Corund Local Council;
Value: 1 000 000 Euro.

Sălsig,  Maramureş county

-    Mechanical-biological wastewater treatment plants  with a capacity of Q = 600 m3/day;
-    Construction of 9.000 m sewage system
-    11 pumping stations;
-    SAPARD program;
-    Implementation period: 2006-2006 (12 months);
-    Beneficiary: Sălsig Local Council;
Value: 1 000 000 Euro.

Zalău, Cehu Silvaniei, Șimleu Silvaniei și Jibou, Sălaj county



-    Rehabilitation of the water distribution systems in the urban areas of the Someș – Tisa hydrographic basin, counties Cluj -  Sălaj;
-    Construction of 63 000 m water distribution network;
-     Construction of 3 pumping stations of Q = 30 m3/h each, one pumping station of Q = 270 m3/h,  chlorination stations;
-    SAMTID PHARE program;
-    Beneficiary: Someș-Tisa Association;

Value: 6 750 000 Euro.

Sâncraiu, Cluj county


-    Construction of sewage system and wastewater treatment plants;
-    Mechanical-biological wastewater treatment plants with a capacity of 250 m3/day;
-    9.000 m sewage system and 3 pumping stations;

Value: 950 000 Euro.

Jucu de Sus, Cluj county


-    Construction of external networks at the NOKIA Industrial     Park;
-    Beneficiary: GOLDBECK GmbH.- Germany;
-    Water supply DN 160 - 600 m;
-    External hydrant network DN 160 - 1.900 m;
-    Sprinkler network DN 300 - 1.200 m;
-    Natural gas supply network DN 125 – DN 250, 600 m;
-    Sewage DN 160 – DN 200, 1.000 m;
-    Rainwater drainage DN 200 – DN 1.200, 2.000 m;
-    1 hydrocarbon separator Q = 883 l/s;
-    1 sand separator Q = 12 l/s;

Value: 950 000 Euro.